Emirates Nuclear Energy Corporation
Emirates Nuclear Energy Company 別名
2009-12-01
United Arab Emirates
Nuclear power plant development and operation
Nuclear energy program implementation
Nuclear workforce development
Nuclear investment and partnership development
SMR research and development
Clean molecule production
Civil nuclear development support
Nuclear energy consulting services
Nuclear power generation
Electricity generation
Nuclear-Related Products & Services
Nuclear-related materials and services
Maintenance services for nuclear plants
Component manufacturing for nuclear plants
Vendor education
Localization process
Operate and maintain the Barakah Nuclear Energy Plant
Maintenance, testing, calibration, NDE, in-service inspections, equipment replacement and upgrade, e
Procurement of non-nuclear related products and services for nuclear plant
Consulting services
Abu Dhabi, United Arab Emirates
会社名
Group 親会社 子会社 得意先 仕入先 業務提携 銀行等 株主等
グループ会社 親会社 子会社 得意先 仕入先 業務提携 銀行・融資・与信 出資・持分・株主
Group 子会社

37 件
日付概要
2008年04月 Publication of the UAE Policy on the Peaceful Use of Nuclear Energy
2009年10月 UAE adopts its Federal Nuclear Law
2009年12月 Launch of the Emirates Nuclear Energy Corporation and Prime Contractor selected
2010年04月 ENEC submits environmental assessment and license applications for preliminary work at Barakah site
2010年07月 The UAE’s Federal Authority for Nuclear Regulation (FANR) approves license requests for preliminary site preparation at Barakah
2010年12月 ENEC submits construction license application for Barakah Units 1 and 2
2012年07月 FANR issues construction license for Barakah Units 1 and 2
2012年07月 Pouring of safety-related concrete for Unit 1
2013年03月 ENEC submits construction license application for Barakah Units 3 and 4
2013年05月 Pouring of safety-related concrete for Unit 2
2013年11月 ENEC completes containment liner installation for Unit 1
2014年04月 ENEC unveils state-of-the-art Simulator Training Center at Barakah
2014年05月 Unit 1 reactor vessel installation
2014年07月 Reactor vessel setting for Unit 1
2014年09月 Pouring of safety-related concrete for Unit 3
2015年01月 ENEC completes concrete dome for Unit 1 reactor containment building
2015年01月 ENEC completes artificial reef off coast of Barakah
2015年03月 ENEC submits operating license application for Units 1 and 2
2015年06月 Unit 2 reactor vessel installation
2015年07月 Second full scope APR-1400 training simulator installed at Barakah
2015年09月 Unit 2 steam generators installed
2015年09月 Pouring of safety-related concrete for Unit 4
2015年11月 ENEC completes containment liner installation for Unit 2
2016年02月 ENEC and Abu Dhabi Transmission & Despatch Company agreement
2016年02月 Unit 1 Cold Hydrostatic Testcompleted
2016年04月 Unit 2 Reactor Containment Building completed
2016年07月 Unit 1 Structural Integrity Test and Integrated Leak Rate Test completed
2016年07月 Unit 3 reactor vessel installed
2016年08月 Unit 3 steam generators installed
2016年10月 Financial Close
2016年10月 ENEC and Korea Electric Power Corporation Joint Venture
2016年11月 Barakah One Company and Abu Dhabi Water and Electricity Company Power Purchase Agreement
2017年01月 Barakah Units 3 & 4 Enter Next Phase of Construction
2017年02月 Unit 4 condenser installed
2017年03月 Unit 3 Reactor Containment Liner Plate and Reactor Containment Building completion
2018年03月 Unit 1 construction completion
2019年07月 First batch of Senior Reactor Operators and Reactor Operators are certified by FANR