1983-08 Decision to introduce regional heating and cooling (Yokohama City) <August>: Minato Mirai 21 Heat Supply Business Company Establishment Council <August>: (Yokohama City, Mitsubishi Estate, Tokyo Electric Power, Tokyo Gas)
1983-08 City of Yokohama decides policy on introduction of DHC.
1983-08 Conference is held to establish MM21 DHC as an operating company.
1986-10 Minato Mirai 21 Heat Supply Corporation Founding General Meeting <October>: Company registration completed <October>
1986-10 General Meeting of Shareholders is held to establish Minato Mirai 21 District Heating and Cooling Co., Ltd. (MM21 DHC).
1986-10 Registration of company establishment is complete.
1987-12 Acquisition of heat supply business permit <December>: Center plant construction start <December>
1987-12 Approval is obtained for a heating and cooling supply business.
1987-12 Construction begins on Center Plant.
1989-02 Construction of Center Plant is completed.
1989-03 Supply regulations are approved.
1989-04 Yokohama Expo <April–October>: Yokohama Maritime Museum (now Yokohama Minato Museum) <April>: Center plant completion <February>: Supply regulation approval <March>: Start of heat supply <April>
1989-04 Heating and cooling supply begins.
1989-04 Yokohama Maritime Museum (now Yokohama Port Museum).
1989-04 Yokohama Exotic Showcase (YES ’89).
1991-04 Minato Mirai 21 & Clean Center <April>
1991-04 Minato Mirai 21 Clean Center.
1991-07 Pacifico Yokohama <July>
1991-07 PACIFICO YOKOHAMA.
1993-07 Yokohama Landmark Tower <July>
1993-07 Yokohama Landmark Tower.
1993-08 Yokohama Bank Head Office Building <August>
1993-08 The Bank of Yokohama Head Office Building.
1994-03 Center plant expansion construction completion and latent heat storage system completion <March>
1994-03 Center Plant expansion project is completed. Latent heat storage system is completed.
1994-04 KDX Yokohama Minato Mirai Tower <April>
1994-04 KDX Yokohama Minato Mirai Tower.
1994-09 Start of the second plant construction〈September〉
1994-09 Construction begins on No. 2 Plant.
1995-09 Keiyu Hospital〈September〉
1995-09 Keiyu Hospital.
1996-10 Company founding 10th anniversary〈October〉
1996-10 MM21 DHC celebrates its 10th anniversary.
1997-06 Nippon Steel Yokohama Building〈June〉
1997-06 Completion of the second plant construction〈June〉
1997-06 Nisseki Yokohama Building.
1997-06 Construction of No. 2 Plant is completed.
1997-07 Queen's Tower A〈July〉 : Queen's Square Yokohama〈July〉 : Grand Mall Park Cross Patio〈July〉
1997-07 Queen’s Tower A.
1997-07 Queen’s Square YOKOHAMA.
1997-07 Grand Mall Park Cross Patio.
1998-01 Supply Area Change Permit (January)
1998-01 Change of supply area is approved.
1999-04 Yokohama Media Tower〈April〉
1999-04 Yokohama Media Tower.
2000-04 Kanagawa Prefectural Police Minato Mirai Branch Office〈April〉
2000-04 Kanagawa Prefectural Police Minatomirai Koban.
2000-09 Cross Gate〈September〉
2000-09 CROSS GATE.
2001-04 Approval of supply regulation change (rate revision: reduction)〈April〉
2001-04 Change of supply regulations is approved (change of fees: reduction).
2001-05 Installation of large absorption chiller (5,000 RT) at the second plant〈May〉
2001-05 A large absorption chiller (5,000 RT) is installed in No. 2 Plant.
2001-08 Yokohama Museum of Art〈August〉
2001-08 Yokohama Museum of Art.
2003-02 M.M. Towers〈February〉
2003-02 M.M.TOWERS.
2003-04 Implementation of supply regulation detailed rules change〈April〉
2003-04 Enforcement bylaws of supply regulations are changed.
2004-02 Fujisoft Building〈February〉
2004-03 Kenmin Kyosai Plaza Building〈March〉
2004-03 Leaf Minato Mirai〈March〉
2004-04 Minato Mirai Station〈April〉
2004-04 Approval of supply regulation change (rate revision: reduction)〈April〉
2004-04 Approval of supply conditions other than supply regulations (annual high-load contract) <April>
2004-04 Change of supply regulations is approved (change of fees: reduction)
2004-04 Supply conditions other than the supply regulations are approved (yearly high-load agreement)
2004-09 Minato Mirai Business Square〈September〉
2006-10 20th Anniversary of Company Establishment <October>
2006-10 MM21 DHC celebrates its 20th anniversary.
2007-03 M.M.TOWERS FORESIS <March>
2007-04 Change of supply regulations is approved (change of fees: reduction)
2007-06 Minato Mirai Mid-Square The Tower Residence <June>
2007-11 Brillia Grande Minato Mirai <November>
2007-12 MM Park Building <December>
2007-12 Pacific Royal Court Minato Mirai Ocean Tower <December>
2008-06 Installation of electric turbo refrigerator (4,000RT) at the second plant <June>
2008-06 Electric centrifugal chiller (4,000 RT) is installed in No. 2 Plant.
2008-07 Pacific Royal Court Minato Mirai Urban Tower <July>
2008-10 Synclon Inc. Headquarters Building Main Building <October>
2009-05 Nissan Motor Corporation Global Headquarters <May>
2009-06 Installation of electric turbo refrigerator (5,000RT) at the second plant <June>
2009-06 Electric centrifugal chiller (5,000 RT) is installed in No. 2 Plant.
2009-12 Yokohama Blue Avenue <December>
2010-03 Hulic Minato Mirai <March>
2010-03 Fujifilm Business Innovation Co., Ltd. Yokohama Minato Mirai Office <March>
2010-04 Approval of supply regulation change (rate revision: reduction) <April>
2010-04 Change of supply regulations is approved (change of fees: reduction)
2010-06 Minato Mirai Center Building <June>
2010-06 Installation of two absorption refrigerators (3,000RT) at the second plant <June>
2010-06 Two absorption chillers (3,000 RT) are installed in No. 2 Plant.
2010-12 Installation of a furnace tube fire-tube boiler (36t/h) at the second plant <December>
2010-12 Furnace-type fire-tube boiler (36 t/h) is installed in No. 2 Plant.
2011-07 Installed absorption chiller (3,000 RT) at Plant 2 (July)
2011-07 Absorption chiller (3,000 RT) is installed in No. 2 Plant.
2011-10 Minato Mirai Grand Central Tower <October>
2012-03 Yokohama Mitsui Building (March)
2013-06 MARK IS Minato Mirai (June)
2013-07 Completion of cooling water interconnection pipe on the Sakae-Honcho line (July)
2013-07 Construction of Sakaehoncho Line cold-water piping is completed.
2014-04 Yokohama Ai Mark Place (April)
2014-09 Syncron Co., Ltd. Headquarters Building New Building (September)
2014-09 Installed boiler (36 t/h) with furnace tube smoke pipe at Plant 2 (September)
2014-09 Furnace-type fire-tube boiler (36 t/h) is installed in No. 2 Plant.
2015-03 Global Learning Center (March)
2015-06 Installed two absorption chillers (3,000 RT) at Center Plant (June)
2015-06 Two absorption chillers (3,000 RT) are installed in Center Plant.
2016-03 Installed inverter turbo chiller (5,400 RT) at Center Plant (March)
2016-03 Inverter centrifugal chiller (5,400 RT) is installed in Center Plant.
2016-04 Established new heat supply agreement (new tariff introduction & price reduction) (April)
2016-04 New heating and cooling supply and demand agreement is established (new fee schedule is established (lower fees)).
2016-08 Minato Mirai Gakuen Building (August)
2016-09 OK Minato Mirai Building (September)
2016-10 Company founded 30th anniversary (October)
2016-10 MM21 DHC celebrates its 30th anniversary.
2017-02 Yokohama Nomura Building (February)
2017-03 Blanz Tower Minato Mirai (March)
2017-03 Blue Harbor Tower Minato Mirai (March)
2017-03 Prime Coast Minato Mirai (March)
2017-08 OCEAN GATE MINATO MIRAI (August)
2018-11 Shiseido Global Innovation Center (November)
2019-01 Installed gas engine combined heat and power system (2,000 kW) and disaster relief generator (2,000 kVA) at the central plant (January)
2019-01 Gas-engine co-generation system (2,000 kW) and emergency backup generator (2,000 kVA) are installed in Center Plant.
2019-03 Signed an educational cooperation agreement with Yokohama Municipal Minatomirai Honmachi Elementary School (March)
2019-03 30th anniversary of heat supply start (continuous supply / nonstop operation) (March)
2019-03 Educational cooperation pact is concluded with Minatomiraihoncho Elementary School.
2019-03 MM21 DHC celebrates the 30th anniversary of the start of heating and cooling supply (continuous supply/non-stop operation).
2019-03 MM21 DHC joins the Smart City Public-Private Partnership Platform.
2019-06 Yokohama Anpanman Children's Museum (June)
2019-08 Shinkoshima Station (August)
2019-08 Participated in the Smart City Public-Private Partnership Platform (August)
2019-08 Furnace-type fire-tube boiler (36 t/h) is installed in No. 2 Plant.
2019-09 Keikyu Group Headquarters (September)
2019-12 Installed a furnace tube smoke pipe boiler (36 t/h) at the second plant (December)
2020-01 KT Building
2020-02 Yokohama Grand Gate
2020-04 Pacifico Yokohama North
2020-04 Yokohama Bay Court Club Hotel & Spa Resort The Kahara Hotel & Resort Yokohama
2020-04 Pia Arena MM
2020-09 Added emergency oil tank to central plant (total 150 kL)
2020-10 Murata Manufacturing Co., Ltd. Minatomirai Innovation Center
2020-12 Kanagawa University Minatomirai Campus
2020-12 Additional emergency oil tanks are built at Center Plant (total of 150kL).
2021-03 Tokyo Metropolitan Expressway Company Kanagawa Bureau
2021-05 Installed one absorption refrigerator (3,000 RT) and two electric turbo refrigerators (5,400 RT) at the second plant
2021-05 One absorption chiller (3,000 RT) and two electric centrifugal chillers (5,400 RT) are installed in No. 2 Plant.
2021-06 Obtained 'Superior' certification in Yokohama City SDGs certification system 'Y-SDGs'
2021-06 MM21 DHC obtains a Superior rating in the Y-SDGs (Yokohama SDGs certification program).
2021-10 Yokohama Gate Tower
2021-12 LG YOKOHAMA INNOVATION CENTER
2021-12 Install a furnace tube smoke pipe boiler (36t/h) at the center plant.
2021-12 Furnace-type fire-tube boiler (36 t/h) is installed in Center Plant.
2022-03 Minatomirai 44 Block Building
2022-04 Participation in the decarbonization pioneer region
2022-04 MM21 DHC joins the Decarbonization Leading Area project.
2022-06 Install absorption chillers (3,000RT one unit, 2,000RT one unit) at the second plant.
2022-06 Two absorption chillers (3,000 RT, 2,000 RT) are installed in No. 2 Plant.
2022-09 Keiyu Hospital Mirai Hall
2023-02 Yokohama Connect Square
2023-05 Install an inverter turbo chiller (5,400RT one unit) at the center plant.
2023-05 An inverter centrifugal chiller (5,400 RT) is installed in Center Plant.
2023-05 A heat-storage electric centrifugal chiller (while storing heat: 2,000 RT) is installed in Center Plant.
2023-07 Install an electric turbo chiller for thermal storage (2,000RT one unit during storage) at the center plant.
2023-07 Install an inverter turbo chiller (5,400RT one unit) and an electric turbo chiller (4,400RT one unit) at the second plant.
2023-07 An inverter centrifugal chiller (5,400 RT) and an electric centrifugal chiller (4,400 RT) are installed in No. 2 Plant.
2023-08 Music Terrace
2024-04 Yokohama Symphostage
2024-04 Start of carbon offset service for heat.
2024-04 Heating-and-cooling carbon offset service is launched.
2024-04 Two absorption chillers (3,000 RT each) are installed in Center Plant.
2024-06 Install two absorption chillers (3,000RT two units) at the center plant.
2024-06 Install one inverter turbo chiller (5,400RT) at the second plant.
2024-06 An inverter centrifugal chiller (5,400 RT) is installed in No. 2 Plant.
2025-04 Launch of environmentally value-added heat tariff menu.
2025-04 Environmental-value-added Heating and Cooling is launched.
2025-04 Heating demand visualization service is launched.
2025-06 Start of heat demand visualization service.
2025-06 Install an electric turbo chiller for thermal storage (2,000RT one unit during storage) at the center plant.
2025-06 A heat-storage electric centrifugal chiller (while storing heat: 2,000 RT) is installed in Center Plant.