Held the founding meeting of a new company (our company) established through joint investment by the fisheries, port operation, and refrigeration industries based on the Tokyo Port Second Revision Port Plan by Tokyo Metropolitan Government
Establishment of the company, capital of 100 million yen
Special maintenance burden for Oi Fisheries Head Pier, first installment of 460 million yen, Tokyo Metropolitan Government bonds underwritten
Preparation completed for the construction of Refrigerated Warehouse No. 1 (40,000 tons), scheduled to start, but construction postponed temporarily due to economic upheaval caused by oil shocks and other factors
First capital increase of 100 million yen, new capital of 200 million yen
Second installment of the special maintenance burden for Oi Fisheries Head Pier, 186 million yen, Tokyo Metropolitan Government bonds underwritten
Completion of pier construction at Oi Fisheries Head Pier (450 meters, 12 meters depth)
Commencement of Phase 1 construction (Buildings 1, 2, and 3)
Second capital increase of 200 million yen, new capital of 400 million yen
Third capital increase of 200 million yen, new capital of 600 million yen
Completion and start of operation of Refrigerated Warehouse No. 1 (May), 40,000 tons (total operational tonnage)
Establishment of Oi Fisheries Pier Association
Completion and start of operation of Refrigerated Warehouse No. 2 (April), 80,000 tons (total operational tonnage)
Fourth capital increase of 200 million yen, new capital of 800 million yen
Completion of Phase 1 construction
Completion and start of operation of Refrigerated Warehouse No. 3 (May), 120,000 tons (total operational tonnage)
Relocation of headquarters functions to Oi Fisheries Head Pier
Commencement of Phase 2 construction (Buildings 4 and 5)
Fifth capital increase of 160 million yen, new capital of 960 million yen
Completion and start of operation of Refrigerated Warehouse No. 4 (August), 186,000 tons (gross operating tonnage)
Relocation of the office to the new office building attached to Warehouse No. 5
Completion of the second phase construction
Completion and start of operation of Refrigerated Warehouse No. 5 (August), 261,000 tons (gross operating tonnage)
Establishment of Logistics Countermeasures Office (currently: Logistics Countermeasures Department)
Start of shared use of pallets for cargo handling inside the pier
Completion of air conditioning work in the sorting room
Completion of air conditioning work in all cargo handling rooms
Implementation of entry/exit restrictions based on SOLAS treaty
Completion of installation of 21 vertical conveyors in all buildings
Completion of high-voltage substation storm surge and tsunami countermeasure work