Completed secondary backfilling of the site; obtained approval for safety facility design (Safety Design Review No. 2024-001).
Completed secondary backfilling of the site; held project commencement ceremony.
Completed procurement of smelting area equipment and signed equipment purchase contracts.
Obtained planning and construction permits for the front-of-factory office unit and commenced construction of the front-of-factory area.
Construction of the front-of-factory unit commenced; completed procurement of fans and vehicle weighing equipment.
Front-of-factory Building 1 entered roof‑finishing stage; completed procurement of disc casting machines and anode furnaces.
Front-of-factory Building 1 topped out; Building 2 auxiliary structure under construction; obtained planning and construction permits for 15 production area units.
Completed planning and construction permits for 15 production area units; finished procurement of water treatment equipment.
Initiated bidding for large equipment such as electrolyzers and sulfuric acid units; began construction of 15 reported production area units.
Designed chemical water treatment plant units and prepared preliminary procedures for reporting.
Designed oxygen generation station area, prepared reporting procedures, and sought to obtain corresponding planning and construction permits.
§07
News
10 ARTICLES
Ball Mill and Semi-automatic Ball Mill at the Slag Plant Successfully Started, Signaling the Final Push for Project Production!
The ball mill and semi-automatic ball mill at the slag plant were successfully started and commissioned in a single operation, running smoothly with all process parameters meeting standards, marking the successful completion of the core grinding system commissioning. The project construction has officially entered the final push phase for production, with on-site staff and management fully acknowledging the achievements of the hard work.
Furnace Fire Marks the Successful Ignition of the YNK Jianfa Shenghai Multi-Metal Recycling Project—Copper Industry Shines
The multi-metal recycling project of YNK Jianfa Shenghai Nonferrous Chemical Co., Ltd. successfully ignited on September 12, 2026, marking the entry of the fire-based system into the kiln phase. Since the project began in September 2023, it has undergone several critical construction milestones, including the foundation construction push in August 2024, construction operations in November 2025, and furnace body masonry in March 2026. This ignition ceremony will simultaneously launch the full-system hot-phase linked trial run, ensuring reliable operation of equipment, instruments, interlocks, and self-control systems, laying the foundation for subsequent production.
Major Breakthrough! 90-Meter Self-Standing Chimney of Yingkou Jianfa Shenghai Copper Smelting Project Successfully Hoisted and Installed!
Yingkou Jianfa Shenghai Nonferrous Chemical Co., Ltd. announced that the 90-meter self-standing chimney has been successfully hoisted and installed, marking a key milestone in the construction of the exhaust gas treatment facility. The chimney was constructed by Hysui Chimney Technology (Lianyungang) Co., Ltd., and no safety incidents occurred during the hoisting process, demonstrating professional expertise. This achievement lays the foundation for subsequent equipment commissioning and production, and the project will continue to advance to the system commissioning stage, aiming for early production.
Yingkou Jianfa Shenghai Copper Smelting Furnace Construction Officially Commences
On March 15, 2026, Yingkou Jianfa Shenghai Nonferrous Chemical Co., Ltd. held a groundbreaking ceremony for the construction of the side-blown furnace, top-blown furnace, and anode furnace at the project site. This construction phase is the core preliminary step of the fire-based system and will directly affect the stable operation of the subsequent smelting production line. The contractor pledged to strictly adhere to quality and safety standards, ensuring the project is delivered on time and with high quality, laying a foundation for the early commissioning of the project.
Two 80 MVA transformers have been successfully positioned at the 220 kV substation of Yingkou Jianfa Shenghai Nonferrous Metallurgy Co., Ltd., marking a key breakthrough in construction of the project's power infrastructure. The substation is the plant's energy hub, ensuring electricity for critical production systems. The team maintained strict safety and quality controls and successfully met the project milestone.
Yingkou Jianfa Shenghai Nonferrous Metallurgy's New Journey in 2026
In 2025, Yingkou Jianfa Shenghai completed multiple construction projects and achieved high-quality development. The company continued making breakthroughs in building its copper industry cluster, uniting to meet challenges. Looking ahead, it will continue moving forward with determination.
Successful Hoisting of First Electrolytic Cells at Yingkou Jianfa Shenghai Nonferrous Technology Co., Ltd.
On October 21, 2025, the first electrolytic cells at the electrolysis plant of Yingkou Jianfa Shenghai Nonferrous Technology Co., Ltd. were successfully hoisted, marking the project's entry into a key equipment installation phase. The operation demonstrated effective teamwork and technical capability, laying a foundation for smooth project progress. As core equipment, the copper electrolytic cells feature corrosion resistance, insulated sealing, and structural stability.
Successful Hoisting of 'Super-Large' Ball Mill Shell at Yingkou Jianfa Shenghai Copper Smelting Project
On November 25, 2025, Yingkou Jianfa Shenghai Nonferrous Chemical Co., Ltd. successfully hoisted the shell of a super-large ball mill for its slag beneficiation project. This key step marks the project's entry into a substantive construction phase and lays a foundation for high-quality corporate development. Company leaders and project representatives said they will continue advancing construction to ensure the project reaches production as scheduled.
Notice on Strengthening Safety Management During the 2025 Mid-Autumn Festival and National Day Holidays
This notice calls for strengthened safety management during the 2025 Mid-Autumn Festival and National Day holidays. The company will take measures to ensure safety and stability during the holiday period. Relevant departments must fulfill their safety responsibilities and protect production operations and personnel.
Notice on Strengthening Safety Management During the 2025 Mid-Autumn Festival and National Day Holidays
This notice calls for strengthened safety management during the 2025 Mid-Autumn Festival and National Day holidays. The company will take measures to ensure safety and stability during the holiday period. Relevant departments are required to fulfill their safety responsibilities and ensure the safety of production and operations.