April: Establishment of Delica Ace Co., Ltd. in Kawaguchi City, Saitama Prefecture
July: Factory construction commenced (completed November)
December: Operation commenced
February: Start of Kawaguchi Co-Distribution Center (center vendorization)
April: Kawaguchi Factory expansion completion ceremony
January: Kawaguchi Factory expansion (expansion of sorting area)
July: Kamio Factory (chilled cooked bread production) operation commenced
February: Investment in Peji Profoz Co., Ltd. (production of seasoning oil tofu for Inari Sushi)
March: Kamio First Factory expansion (pasta)
April: 10th anniversary of founding
March: Kamio Second Factory (rice ball dedicated) operation commenced
April: Yamagata Factory operation commenced
March: Kamio Second Factory expansion
August: Dissolution of investment in related company Benkama Delica Ace Co., Ltd.
July: Kamio First Factory NDF HACCP certification
January: Consolidation of Kawaguchi Factory to Kamio Factory
February: Kamio Second Factory NDF HACCP certification
April: Relocation of head office to Kamio business premises
December: Sorting expansion of Kamio Second Factory
ISO9001 certification acquisition
February ISO14001 Certification Acquisition
April 20th Anniversary of Founding
March Yamagata Plant Expansion
OHSAS18001 Certification Acquisition
June Consolidation of Yamagata Plant to Ageo Plant
September New Sorting Building Opening
February Production Headquarters Second Plant New Rice Cooker Building Opening
May Vegipro Foods (Inc.) Investment Dissolution
February Station Front Branch Opening
April 30th Anniversary of Founding
May Production Headquarters First Plant FSMS Certification Acquisition
August Production Headquarters Second Plant FSMS Certification Acquisition
December Transition from OHSAS18001 to ISO45001 Certification Acquisition
September Consolidation of Station Front Branch into Ageo Office